Description of completed project
Contractor: OP Systems Ltd.
Employer: Hitachi Energy Bulgaria Ltd.
Project: Relocation and extension of control room in office relocation
I. General project information
OP Systems Ltd. successfully completed a complex project related to the relocation of the office of Hitachi Energy Bulgaria Ltd. to a new building, as well as the expansion and modernization of the control room. The activities included dismantling, moving, transporting, re-installation of existing equipment as well as supply and installation of new Samsung professional displays and Vogel's components.
The main objective was to build a larger, technologically advanced control room with a total of 12 new Samsung frameless professional displays, located on Vogel's specialized professional construction, ensuring reliability, precision and flexibility in operation.
________________________________________
II. Control room relocation works carried out
1. Dismantling and packing of equipment
1. Dismantling and packing of 10 pcs 46″ displays
2. Disassembly and installation of professional ceiling stand - 1 pc.
3. Dismantling and packing of projector and projector stand - 1 pc.
4. Dismantling and packing of speakers - 2 pcs.
5. Dismantling and packing of amplifier and microphones - 2 pcs.
________________________________________
III. Addition to the existing stand
Additional Vogel's modules were added to ensure compatibility with the expanded configuration:
1. Horizontal adapter PFB 3419 BL - 2 pcs.
2. Horizontal connection kit PFA9104 - 1 pc.
3. Vertical display rails PFS3304 - 4 pcs.
4. Fixing element for floor PFA 9103 - 2 pcs.
Installation on the existing system
1. Installation of the elements to the existing stand - 1 pc.
2. Installation of 10 pcs. 46″ displays on the ceiling stand - 10 pcs.
________________________________________
IV. New stand for Samsung professional displays
For the expanded control room, new Vogel's components were supplied and integrated to build a robust structure for 12 new Samsung displays:
1. Vertical adapter PFF 7965 - 3 pcs.
2. Vertical profile PUC2933 - 3 pcs.
3. Horizontal adapter PFB3427 BL - 3 pcs.
4. Horizontal adapter PFB3419 BL - 3 pcs.
5. Horizontal connection kit PFA9104 - 3 pcs.
6. Vertical 3D display rails PFS3504 - 12 pcs.
7. Fixing element for floor PFA 9132 - 3 pcs.
8. Installation of the entire structure with the displays - 1 pc.
________________________________________
V. New equipment delivered and installed
1. Professional Displays
- SAMSUNG LH55VMBUBGBXEN - 12 pcs.
Frameless displays suitable for video walls and 24/7 operation.
2. Media player
- Samsung SBB-SS08NV2XEN - 2 pcs.
3. Wiring
- Install HDMI and LAN cables for all new displays and players
________________________________________
VI. Result
Upon completion of the project, Hitachi Energy Bulgaria Ltd. has a modernized and significantly expanded control room equipped with professional displays. The new Vogel's construction ensures maximum stability, perfect arrangement and trouble-free operation.
OP Systems Ltd. performed the relocation and integration without interruption to the operational processes, taking into account the high requirements for reliability and precision.